We have a 'punch list' inspection scheduled for this afternoon for my project across the river, renovating an old double-house into transition apartments for chronic homeless clients of a local social service agency. In theory, the project will be almost complete. We'll be looking for bits and pieces that need finishing before the clients move in, with a completion and occupancy date of February 28.

"In theory, theory and practice are the same. In practice, they are not."

The agency would _really_ like those apartments available. Some of the clients will lose their housing vouchers if they can't find a roof to rent.

Thirty years of construction industry experience suggests that we will find more than a week's worth of work in need of completion.

Added words to SIGNATURES, casualty count on the first explosion seems limited to one broken leg and a lot of ruined equipment. Fat Wizard hasn't learned about the second blast yet.

Profile

jhetley: (Default)
jhetley

August 2025

S M T W T F S
      1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31      

Style Credit

Expand Cut Tags

No cut tags
Page generated Sep. 1st, 2025 08:55 am
Powered by Dreamwidth Studios